The AVCA Board of Directors obtained pricing from four highly qualified asphalt vendors and approved A & Y Asphalt Contractors, Inc. to perform AVCA’s asphalt work in 2023. The scheduled work effecting AYSO begins Monday, September 18th and runs through October 6th.
The asphalt work affecting AYSO is:
September 18-22: Aliso Viejo Community Park Parking Lot Mill and overlay the entire parking lot. Each day the parking lot will be completely off limits for vehicles/pedestrians.
September 28: Ridgecrest Parking Lot Crack fill, slurry seal and restriping, completely off limits for vehicles/pedestrians for 24 hours.
October 6th: Argonaut Park Parking Lot Crack fill, slurry seal and restriping, completely off limits for vehicles/pedestrians for 24 hours.
For September 18-22 at the Aliso Viejo Community Park parking lot the contractor will be blocking off the entire parking lot each day. Please park on the street and stay off the parking lot during construction.